⏱️ Time and Work
Day 2 | ⏱️ Part of 2-Hour Commercial Math Block | TCS Interview Prep
📌 Subtopics
- Individual work rate problems
- Combined work (two or more workers)
- Pipes and cisterns
- Alternate day work problems
- Work and wages
- Efficiency-based problems
📖 Comprehensive Notes
1. Individual Work Rate
Work done is the product of rate (efficiency) and time:
- If a person A can complete a piece of work in days, then:
- LCM Method (Highly Recommended): Assume the Total Work is the LCM of the times taken by individuals. This avoids working with fractions.
Example: A can do a work in days and B in days. What is their daily efficiency if total work is assumed using the LCM method? . . .
2. Combined Work
- If A takes days and B takes days to finish a work:
- Using the LCM Method:
Example: Using the previous example, how long will A and B take together? . . days.
3. Pipes and Cisterns
This is identical to Time and Work, but with negative work (leaks or outlet pipes).
- Inlet pipe (fills) Positive work ().
- Outlet pipe (empties) / Leak Negative work ().
- If an inlet pipe fills a tank in hours and an outlet empties it in hours (where ):
Example: Pipe A can fill a tank in hours, and Pipe B can empty it in hours. If both are opened together, how long to fill the tank? Let total capacity . Pipe A efficiency . Pipe B efficiency . Net efficiency . Time hours.
4. Alternate Day Work
Workers work one after the other on alternate days.
- Calculate the work done in one full cycle (e.g., days if two workers).
- Find the number of complete cycles needed to get close to the total work, then calculate the remaining work and time for the next worker.
Example: A can do a work in days and B in days. If they work on alternate days starting with A, when is the work done? . , . In days ( cycle), work done . In cycles ( days), work done . Remaining work . On day , A works and does exactly (since his eff is ). Total time days.
5. Work and Wages
Wages are distributed in proportion to the actual amount of work done by each individual.
- If people work for the same duration, wages are divided in the ratio of their efficiencies.
- If they work for different durations, wages are divided in the ratio of the units of work completed ().
Example: A can do work in days and B in days. They work together and earn . Find A’s share. Since they worked for same duration, wage ratio efficiency ratio . A’s share .
6. Efficiency-Based Problems
“A is times as efficient as B” .
- Since efficiency is inversely proportional to time:
Example: A is twice as efficient as B and takes days less than B to finish a work. Find B’s time. Let B take days, so A takes days. Since A is twice as efficient, A takes half the time: days.
🌐 Learning Resources
| Resource | Link |
|---|---|
| IndiaBIX — Time & Work | indiabix.com |
| GFG — Time and Work | geeksforgeeks.org |
| PrepInsta — TCS Time and Work | prepinsta.com |
| Khan Academy — Rates & Ratios | khanacademy.org |
| IndiaBIX — Pipes & Cisterns | indiabix.com |
✅ Practice Links
| Platform | Link |
|---|---|
| PrepInsta — Time & Work Questions | prepinsta.com |
| IndiaBIX — Time & Work Problems | indiabix.com |
📝 Key Formulas
If A does work in 'a' days → A's 1 day work = 1/a
Combined rate: 1/a + 1/b = 1/T → T = ab/(a+b)
Pipes & Cisterns:
Filling pipe rate = +1/t
Draining pipe rate = -1/t
Net rate = Sum of all rates
Tip: Use LCM method for faster solving — take LCM of days as total work units.
🔗 Related Topics
- Time Speed and Distance — Rate-based problems with similar structure
- Ratios and Proportion — Efficiency ratios and work sharing
- Equations — Setting up work rate equations
- Allegations and Mixtures — Similar ratio-based problem solving approach
- Percentages — Efficiency as a percentage